Project List

PROJECT LIST (COMPLETED AND ONGOING)

REF

PROJECT TITLE

SCOPE OF WORK

CLIENT

DATE START

COMPLETION DATE

CONTRACT SUM

KB-Saz-58-01

CADANGAN PEMBANGUNACADANGAN MEMBINA DAN MENYIAPKAN 114 UNIT RUMAH TERES 3 THINGKAT (22’ X 75’) DI ATAS SEBAHAGIAN LOT 16748 (PT NO 7718), PRECINT 12, MUKIM RAJA DAERAH PETALING SEKSYEN U13, 40170 SHAH ALAM, SELANGOR DARUL EHSAN – Phase 1A

Supply labour for Reinforced Concrete Works.0

Sazean Development s/b

30-MAR-2010

25-APR-2011

3.85 Mil

KB-Saz-58-02

CADANGAN MEMBINA DAN MENYIAPKAN 114 UNIT RUMAH TERES 3 THINGKAT (22’ X 75’) DI ATAS SEBAHAGIAN LOT 16748 (PT NO 7718), PRECINT 12, MUKIM RAJA DAERAH PETALING SEKSYEN U13, 40170 SHAH ALAM, SELANGOR DARUL EHSAN – Phase 1A

Supply labour and material for brick and plastering work.

Sazean Development s/b

20-AUG-2010

17-SEP-2011

6.8 Mil
1.5 Mil

KB-Saz-58-03

CADANGAN MEMBINA DAN MENYIAPKAN 151 UNIT RUMAH TERES 3 THINGKAT (22’ X 75’) DI ATAS SEBAHAGIAN LOT 16748 (PT NO 7718), PRECINT 12, MUKIM RAJA DAERAH PETALING SEKSYEN U13, 40170 SHAH ALAM, SELANGOR DARUL EHSAN – Phase 1B.

Supply labour and material for Reinforced Concrete Works.

Sazean Development s/b

12-MAR-2011

15-SEP-2013

14.87 Mil

KB-Saz-58-03

CADANGAN MEMBINA DAN MENYIAPKAN 151 UNIT RUMAH TERES 3 THINGKAT (22’ X 75’) DI ATAS SEBAHAGIAN LOT 16748 (PT NO 7718), PRECINT 12, MUKIM RAJA DAERAH PETALING SEKSYEN U13, 40170 SHAH ALAM, SELANGOR DARUL EHSAN – Phase 1B

Supply labour and material for brick works.

Sazean Development s/b

12-MAR-2011

17-OCT-2013

4.26 Mil

KB-Purcon 62

CADANGAN MEMBINA DAN MENYIAPKAN PEMBANGUNAN PERUMAHAN, DI ATAS SEBAHAGIAN SEKSYEN 4 TAMBAHAN, BANDAR BARU BANGI, MUKIM KAJANG, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN

Supply labour and partial material for structure work.

PKNS/Pembinaan Purcon

15-JUN-2011

23-DEC-2013

1.65 Mil

KB-HAB-63

GLOMAC DAMANSARA

Supply labour only for structure work.

Glomac/ HAB

07-JUN-2011

23-JUN-2012

2.5 Mil

KB-Binastra-64

BANK NEGARA SITE B, PACKAGE B, WORKERS QUAR CADANGAN MEMBINA 17 UNIT BANGUNANA PERINDUSTRIAN BERKEMBAR 3 TINGKAT DI ATAS LOT 62416, BUKIT JELUTONG

Earthworks, Building & Infrastructure Works.

Binastra Group

15-NOV-2011

12-OCT-2013

7.5 Mil

AR-HSL-64

CONSTRUCTION AND COMPLETION OF WATER RESERVOIR AND PUMP ROOM, BINTULU, SARAWAK

Building Works.

HSL Group

05-MAY-2012

16-JUL-2013

8.9 Mil

KB-HAB-66

B3, B2, B1 & PART LG STRUCTURE WORKS FOR CADANGAN PEMBAGUNAN PERNIAGAAN YANG MENGANDUNGI:- 1) 3 BASEMEN DAN 1 SUB-BASEMEN TEMPAT LETAK KERETA

Sub-Structure (Labour only)

IOI/ HAB

03-JUL-2012

12-DEC-2013

3.09 Mil

KB-Binastra-68

47 UNIT 3 STOREY SHOP LOTS AT BUKIT SERDANG.

Earthworks.

Binastra Group

03-SEP-2012

22-JAN-2013

0.879 Mil

KB-Binastra-68

47 UNIT 3 STOREY SHOP LOTS AT BUKIT SERDANG

Building & Infrastructure Works.

Binastra Group

03-SEP-2012

On Progress

9.850 Mil

 

 

PROJECT LIST (COMPLETED AND ONGOING)

REF

PROJECT TITLE

SCOPE OF WORK

CLIENT

DATE START

COMPLETION DATE

CONTRACT SUM

KB-Macru-69

2 BLOCK 9 & 15 STORIES OFFICE AND RESIDENTIAL BLOCK AT ARA DAMANSARA. BLOCK E, F AND J

Building works.

Jak Resource BHD

19-NOV-2012

22-DEC-2013

2.3 Mil

KB-Purcon-70

PRIVATE PRIMARY AND SECONDARY INTERNATIONAL SCHOOL (PHASE 1), ON LOT 35085 (GRN 172579), BANDAR BUKIT PUCHONG 2, MUKIM DENGKIL, DAERAH SEPANG SELANGOR DARUL EHSAN.

Super Structure (Labour only)

Pembinaan Purcon

12-DEC-2012

30-SEP-2013

2.855 Mil

KB-Binastra-71

CADANGAN PEMBINAAN YANG MENGANDUNGI: FASA 3:
1 BLOCK MENARA SOHO C-31 TKT (375 UNITS)
1 BLOCK MENARA SOHO D-30 TKT (37 UNITS) CYBERJAYA

Sub & Superstructure Works (Labour only)

Binastra Group Demi Murni Holdings Sdn Bhd

05-AUG-2013

On Progress

6.5 Mil

KB-WCT-72

THE PROPOSED DESIGN, CONSTRUCTION AND COMPLETION OF GOVERNMENT BUILDING (MITI HEADQUARTERS) EXTERNAL WORKS ON PART OF PT 25966 (FORMERLY KNOWN AS PLOT 8) JALAN KHIDMAT USAHA, MUKIM BATU, KUALA LUMPUR..

Building Works.

WCT Berhad

01-APR-2013

On Progress

21.3 Mil

KB-HAB-77

SUPERSTRUCTURE WORKS FOR CADANGAN PEMBANGUNAN PERNIAGAAN YANG MENGANDUNGI : FASA 2
I) SEBUAH RUMAH KOMPLEKS PERNIAGAAN 4 TINGKAT.
II) 3 BASEMENT DAN 1 SUB-BASEMENT TEMPAT LETAK KERETA.
DIATAS SEBAHAGIAN LOT 6, MUKIM DENGKIL, DAERAH SEPANG, SELANGOR DARUL EHSAN UNTUK TETUAN DREAMMONT DEVELOPMENT SDN BHD.

Super Structure (Labour only)

IOI/ HAB

07-MAR-2013

On Progress

2.30 Mil

 

SUPERSTRUCTURE WORKS FOR CADANGAN PEMBANGUNAN PERNIAGAAN YANG MENGANDUNGI : FASA 2
2BLOCK MENARA PEJABAT 30 TINGKAT DI ATAS SEBAHAGIAN LOT 6, MUKIM DENGKIL, DAERAH SEPANG SELANGOR DARUL EHSAN UNTUK TETUAN IOI CITY TOWER ONE SDN BHD AND IOI CITY TOWER TWO SDN BHD

Super Structure (Labour Only).

IOI/ HAB

23-OCT-2013

On Progress

2.766 Mil

 

SUPERSTRUCTURE WORKS FOR CADANGAN MEMBINA 1 BLOK HOTEL 21 TINGKAT (FASA3) YANG MENGANDUNGI 348 BILIK DAN KEMUDAHAN AWAM DIATAS SEBAHAGIAN LOT 6, MUKIM DENGKIL, DAERAH SEPANG, SELANGOR DARUL EHSAN UNTUK TETUAN DREAMMONT DEVELOPMENT SDN BHD.

Super Structure (Labour only).

IOI/ HAB

03-MAR-2014

On Progress

1.25 Mil

KB-TNH -001-14

CADANGAN MENDIRIKAN PEMBANGUNAN BERCAMPUR 3 BLOCK 28 TINGKAT YANG MENGANDUNGI:
1) BLOCK B: 365 UNIT APARTMENT SERVIS 21 TINGKAT,
II) BLOCK C : 168 UNIT APARTMENT SERVIS 21 TINGKAT, TERMASUK 71/2 TINGKAT PODIUM TEMPAT LETAK KERETA DAN 2 TINGKAT BASEMENT TEMPAT LETAK KERETA DI ATAS LOT 30844, BATU 6, JLN SG BESI, MUKIM PETALING, DALAM BANDARAYA KUALA LUMPUR.

Sub & Super Structure (Labour Only) And Architecture-Brickwall, Plastering & Skim Coating Works.

TNH Construction Sdn Bhd

03-FEB-2014

On Progress

Estimation Contract Sum RM18.663 Mil

 

 

 

PROJECT LIST (CURRENT - 2015)

REF

PROJECT TITLE

SCOPE OF WORK

CLIENT

DATE START

COMPLETION DATE

CONTRACT SUM

003/14-WCT

THE PROPOSED CONSTRUCTION AND COMPLETION OF COMMERCIAL OFFICE BUILDING AND EXTERNAL WORKS AT LOT 2C5, PRECINCT 2, PUTRAJAYA.

Supply labour for Reinforced Concrete & Super Structure

WCT Construction Sdn Bhd

7-July-2014

On Progress

Estimation Contract Sum
48 Mil

004/14-MK20-HAB

CADANGAN PEMBANGUNAN PERDAGANGAN YANG MENGANDUNGI :-
II) 1 BLOK 19 TINGKAT PANGSAPURI SERVIS (331 UNIT), DENGAN 5 TINGKAT ARAS BAWAH DAN 1 TINGKAT BESMEN (TEMPAT LETAK KERETA, RUANG PERNIAGAAN DAN KEMUDAHAN) DI ATAS LOT 1881 & 1882, JALAN KIARA, MONT KIARA, MUKIM BATU, KUALA LUMPUR (MK20).

Supply labour for Reinforced Concrete & Super Structure

HAB Construction Sdn Bhd

November 2014

On Progress

6 Mil

 

THE PROPOSED COMMERCIAL DEVELOPMENT (PHASE 3) ON LOT 49682 & 49683, DAERAH PETALING JAYA, JALAN HARAPAN, 46400 PETALING JAYA, SELANGOR DARUL EHSAN.

Supply labour for Suoer Structure

Selangor Dredging Berhad

April 2015

 

23 Mil

 

CADANGAN PEMBANGUNNA 2 BLOK PANGSAPURI (512 UNIT RUMAH MAMPU MILIK) YANG MENGANDUNGI; 4 TINGKAT PODIUM TLK, 1 TINGKAT RUANG KEMUDAHAN (GIMNASIUM, KOLAM RENANG, SURAU, BILIK PERSALINAN, DEWAN SERBAGUNA, BILIK BACAAN & TADIKA), 2 BLOK RUMAH MAMPU MILIK 16 TINGKAT, 1 TINGKAT RUANG TANGKI AIR & BILIK MOTOR LIFT DI ATAS PT 14996 (HSD 118734), JALAN SINAR, TAMAN NAGA EMAS, MUKIM PETALING, WILAYAH PERSEKUTUAN KUALA LUMPUR.

Supply labour for Building, Infrastructure And Mechanical & Electrical Works

Danau Lumayan Sdn Bhd

April 2015

 

88 Mil